Commencing 29th June for approx. 1 month, rock installation and survey operations will be taking place along the route of the Greenlink Interconnector cable across Port Limits.
- MARINERS ARE HEREBY ADVISED that, commencing 29th June for approx. 1 month, rock installation and survey operations will be taking place along the route of the Greenlink Interconnector cable across Port Limits (see chartlet).
- Rock installation operations will be carried out by vessel ‘Simon Stevin’ within Port Limits.
- SIMON STEVIN (IMO: 9464807, Call sign: LXUB, MMSI: 253309000) is a DP2 offshore Subsea rock installation vessel. Her length overall (LOA) is 191.5 metres and her width is 40.0 metres.
- There may be several small Crew Transfer Vessels and Guard Vessels operating in connection with these operations.
- All vessels will maintain a listening watch at all times on VHF Channels 12 & 16 and will be showing the appropriate day shapes and lights as laid down in the Collision Regulations when restricted in ability to manoeuvre.
- Mariners are required to navigate with caution in these areas whilst operations are taking place, to pass by with minimum wake and observe the 500m exclusion zones guarding their operations.
- For further details of the location and status of this vessel whilst within Port Limits, please contact Milford Haven VTS on:
- VHF channel 12
- Telephone 01646 696100
- Email vts@mhpa.co.uk
- Admiralty Charts 2878, 3273, 3274, Imray Y26 & 2600 ATLAS refer.
- A further notice will be issued when works are complete.