NOTICE TO MARINERS - NO. 26 OF 2010 - WORKS TO HAKIN PIER
MILFORD HAVEN PORT AUTHORITY
NOTICE TO MARINERS
NO. 26 OF 2010
WORKS TO HAKIN PIER
1. MARINERS ARE HEREBY ADVISED that, on or about 11th February 2010, works will commence on Hakin Pier (approximate position 51º42.'5 N 005º 02'.4W).
2. The steel steps on the East side will be removed and the East side will be shuttered and concrete works will follow. New stairs will then be installed.
3. The Pier is not to be used during the period of the works as it will be fenced off. A warning notice will be posted.
4. Works are expected to take 16 weeks. A further Notice to Mariners will be issued when Hakin Pier is available for use again.
5. Admiralty chart 3274 and 3275 and Imray C2600.11 refer.
BY ORDER
M C ANDREWS
HARBOURMASTER
Milford Haven Port Authority 9th February 2010
Gorsewood Drive
Milford Haven
Pembrokeshire
SA73 3ER
Tel: 01646 696100
Fax: 01646 696125
Email: enquiries@mhpa.co.uk

ID: 2232 Revised:09/02/2010